Overview
You can use scheduled hours that have already been created for a resource to quickly create allocations.
These allocations are created based on the weekly scheduled hours for a resource. If consecutive weeks contain an equal number of hours, they will be combined into a multi-week allocation.
For example, if one week has 20 hours scheduled and the next week has 30 hours—as shown in Example A below—then they are created as individual weekly allocations. However, if one week has 40 hours scheduled for one week and 40 hours scheduled for the next week—as shown in Example B below—then a single, multi-week allocation of 80 hours is created.
How to Create Allocations from Scheduled Hours
- Navigate to a Resourcing area in Kantata:
- Projects > select a project > Resourcing
- Resourcing > Resource Center > Team Members
- Resourcing > Resource Center > Projects
- From the respective Resourcing page, locate the project or resource you want to create allocations for, then expand the top-level row.
Note: Depending on where you are in Kantata, the order of these rows may vary. For example, the resource row is the top-level row in the Team Members tab. - In the expanded resource or project row, click the More
icon and select Create Allocations. - In the Create Allocations modal that appears, select the timeframe of scheduled hours that you want to create your allocations for:
- Anytime—Selected by default, this option takes all of a resource's scheduled hours and distributes them as allocations.
- After—This option takes only the resource’s scheduled hours that occur on or after the date selected and distributes them as allocations.
- Before—This option takes only the resource’s scheduled hours that occur on or before the date selected and distributes them as allocations.
- Between—This option takes only the resource’s scheduled hours that occur between the two dates selected and distributes them as allocations. Any scheduled hours on the selected dates are also included.
- If you selected an option that requires a date, select a date—or date range—to indicate which scheduled hours you want to create allocations for.
- Indicate under Allocation Type if you want to create Soft or Hard allocations.
- Select Create Allocations. The allocations appear on the Resource Center timeline for the resource.